Week 2 is now officially complete!
Week two has been a massive success for our team of ‘smartbuilders.’ The progress at our new site at the Strabane Business Park has been magic in the last week. Regardless of the bad weather conditions at the beginning of the week, we still remained on schedule.
This week’s developments?
- Foundations have started, a new base for our new manufacturing facility has been formed
- Ground levels are under construction – nearly there
- A cabin has also been delivered to site for admin, lunch breaks and most importantly ‘shelter’
- The offsite hut has been complete which will house all our electrical supply
- and much more…
The Strabane Business Park has been rattled this week with the noise of all our machinery – we send out our apologies to the neighbours affected by the noise and vibrations nearby. We look forward to a new week of good weather and lots of progress!