Week 1 of the KES Group Factory Build
The journey to our brand new manufacturing and office facility at the Strabane Business Park has officially begun. Phase 1 of our new premises started on the 1st April 2019. The diggers landed on site to form our brand new entrance. Following on from this our team of tradesmen began to form the foundations where our new premises will lay.
The KES Group Factory Phase 1 will consist of a 30,000sqft manufacturing and office facility. This premises is due to open up multiple production lines for our modular units. This will allow us to meet the current and growing demand of our customers across Ireland and the wider UK.
We have predicted this build to be complete over the next 35 weeks and will document the ongoing progress of the new KES Group factory. Stay tuned for weekly updates on phase 1 of this exciting project.